REV3 REVIEWED - BLD2021-0088+DESCRIPTION 5.17.2023_2.23.39_PM+3551836AAA
Ankrom Moisan
Architect's Supplemental Instructions
ASI # 009 - Smoke Control System Coordination
Date Issued: 12 May 2023
Project:
Anthology of Edmonds
AM Project #:
184470
Owner:
CA Senior
Contractor:
Catalyst Construction
Architect:
Ankrom Moisan Architects, Inc.
To:
Brenda Clark, Mike Roggeman
cc:
Kurt Sorensen, Eileen Mortenson
The following supplemental instructions are issued in accordance with the Contract Documents. The Contractor shall carry
out the Work in accordance with these supplemental instructions without change in the Contract Sum or the Contract Time.
Performance of the Work in the accordance with these supplemental instructions indicates Contractor's acknowledgement
that there will be no change in the Contract Sum or Contract Time.
Supplemental Instructions:
ASI 009 is provided as a response to the first round of smoke control comments for permit
FIR2023-0030. Provided architectural and structural drawings detailing for new 2 hour
vertical and horizontal shafts at gridline 10/F intersection.
Attachments (if necessary):
1. BLD2021-0088_ASI 009 - Architectural Drawings,pdf
2. BLD2021-0088_AS1009_Structural Drawings.pdf
Issued by:
Signature: �f---`.
Name:
ARCHITECTURE
Firm:
INTERIORS
URBAN DESIGN
Accepted by:
BRANDING
Signature:
Name:
Ankrom Moisan Architects
Firm:
PORTLAND
38 NW Davis Street
Suite 300
Portland, OR 97209
503.245.7100
SEATTLE
1505 5th Avenue
Suite 300
Seattle, WA 98101
206.576.1600
SAN FRANCISCO
1014 Howard Street
San Francisco, CA 94103
415.252.7063
Richard Grimes
Ankrom Moisan Architects, Inc.
05.12.2023
Date
Date