February 23, 2024
Mr. BK Chen
VIA Email: bkchen@gmail.com
RESUB
Feb 23 2024
CITY OF EDMONDS
DEVELOPMENT SERVICES
DEPARTMENT
Geotechnical Plan Review Letter
Chen 210th Street SW Residential Development
7103 — 210th Street SW
Edmonds, Washington
NGA Project No. 1209720
17311-135th Ave. N.E. Suite A-500
Woodinville, WA 98072
(425)486-1669
www.nelsongeotech.com
BLD2023-0692
REVIEWED
BY
CITY OF EDMONDS
BUILDING DEPARTMENT'
Dear Mr. Chen:
This letter presents the results of our geotechnical engineering review of the civil plans for the proposed
Chen 210th Street SW Residential Development project located at 7103 — 210th Street SW in Edmonds,
Washington.
INTRODUCTION
We understand that the proposed development for the property will include the construction of six new
townhome residence structures within the eastern portion of the property along with associated paved
parking areas and underground utilities. We previously prepared a stormwater infiltration evaluation for
the site dated November 12, 2020. In general, we concluded that stormwater infiltration for the planned
site development was feasible from a geotechnical standpoint. We understand that the City of Edmonds
has requested our review of the civil plans to confirm they are consistent with our previous
recommendations in a letter dated August 21, 2023.
For our use in preparing this plan review letter, we have been provided with the following documents:
• Civil plan set titled "HC Townhouse," dated February 9, 2024, prepared by Home Tech.
We have been requested to provide our plan review of the provided civil plans. In the following sections,
we summarize the results of our geotechnical plan review.
Geotechnical Plan Review Letter
Chen 210th Street SW Residential Development
Edmonds, Washington
NGA File No. 1209720
February 23, 2024
Page 2
PLAN REVIEW
We have reviewed the geotechnical aspects of the provided civil plans and found the plans to be in general
compliance with our recommendations as presented in our previous geotechnical report. In our previous
report, we determined that traditional stormwater infiltration systems founded within the granular native
advance outwash soils at depth were feasible within this site. We understand that stormwater within the
site will be directed to flow through a series of catch basins into a gravel -filled infiltration trench system
within the southern portion of the property. The trench will be 36-feet long, 5-feet wide and 4-feet deep.
Based on review of the drainage report, it appears that the infiltration system was sized and designed
based on the long-term design infiltration rate provided in our previous report. We recommend that the
system be fully founded within the native granular advance outwash soils at depth, and NGA be retained
during construction to confirm the soil conditions prior to backfilling the systems. All other
recommendations provided in our previous report should be strictly followed.
CLOSURE
We recommend that NGA be retained to provide monitoring and consultation services during
construction to confirm that the conditions encountered are consistent with those indicated by the
explorations, to provide recommendations for design changes should the conditions revealed during the
work differ from those anticipated, and to evaluate whether or not earthwork activities comply with
contract plans and specifications.
NELSON GEOTECHNICAL ASSOCIATES, INC.
Geotechnical Plan Review Letter
Chen 210th Street SW Residential Development
Edmonds, Washington
NGA File No. 1209720
February 23, 2024
Page 3
We appreciate the opportunity to provide service to you on this project. Please contact us if you have any
questions regarding this letter or require further information.
Sincerely,
NELSON GEOTECHNICAL ASSOCIATES, INC.
Lee S. Bellah, LG
Senior Geologist
2.23.2024
Khaled M. Shawish, PE
Principal
LSB:KMS:dy
NELSON GEOTECHNICAL ASSOCIATES, INC.