HomeMy WebLinkAboutPPW040919Minutes
PARKS & PUBLIC WORKS COMMITTEE MEETING
April 9, 2019
Elected Officials Present Staff Present
Councilmember Kristiana Johnson (Chair) Phil Williams, Public Works Director
Councilmember Dave Teitzel Rob English, City Engineer
Jeannie Dines, Recorder
The meeting was called to order at 7:00 p.m. in the Council Chambers.
1. Authorization to Purchase - 2019 Cues Sewer Video Inspection Truck
Mr. Williams explained the 2019 budget included $1.408M for acquisition of new vehicles. This truck
was budgeted at $425,000, a scheduled replacement of the 2009 of the sewer truck purchased via the
Houston Galveston Area Council purchasing cooperative. The cost after a $50,000 trade-in is $412,000
plus the cost of City logos, radios, etc. He responded to questions regarding the list price of vehicle
before trade-in, approximate service life of the truck, new radio technology, and fuel source (diesel).
Action: Action item for full Council due to amount
2. Authorization for Mayor to Sign Interlocal Agreement with Community Transit for
Commute Trip Reduction 2019-2023
Mr. English explained this will extend the existing CTR interlocal agreement that expires at the end of
2019 until 2023. Edmonds and seven other cities participate in the CRT program. Three
agencies/businesses in Edmonds with 100+ employees (City of Edmonds, Swedish Edmonds Hospital
and Edmonds Family Medicine) meet the CRT requirement. The State provides $1750 for each
business which the City provides to Community Transit to manage the CTR program. He responded to
a question regarding City staff time for the CTR program (4-6 hours/month.)
Action: Schedule on Consent Agenda
3. Report on Construction Bids for the 2019 Overlay Program
Mr. English explained this project went out to bid in March; the City received four bids. The low bid,
$1,307,369, was submitted by Lakeside Industries. The engineer’s estimate was $1,259,198. He
recommended awarding the bid to Lakeside Industries. This year’s program will pave 6.8 lane miles of
city street. Funding for the project is provided by REET 126 and 125 ($450,000 each), General Fund
($500,000) Street Capital Fund ($100,000) and Water Utility Fund ($300,000) for street impacted by
watermain replacement for a total of $1.8M. Staff recommends a 15% construction management and
10% management reserve. The project was bid with two-thirds of the material hot mix asphalt with
Kevlar fibers which is expected to extend the life by 50%.
Discussion followed regarding lane miles paved in 2018 (approx. 7 miles), slurry/chip seal (none this
year), amount of other bids, paving done in previous years via contract with Snohomish County and
economies of scale doing paving with Snohomish County. Councilmember Johnson inquired about a
street off Bowdoin Way where a stormwater project was done but was not included in this year’s or last
year’s overlays. Staff will research.
04/09/19 PPW Committee Minutes, Page 2
Action: Schedule on Consent Agenda
4. Report on Construction Bids for 174th St/71st Ave Storm Improvements Project
Mr. English reported 14 construction bids were received for this project. The low bid was rejected due
to missing documentation. The second low bid, $173,656, was submitted by Redtail. The engineer’s
estimate was $181,000. The proposed construction budget is $225,856 with a 15% construction
management and 15% management reserve. The project will be funded by the Stormwater Utility Fund
422. Staff responded to a question regarding plans for a surface mounted drain pipe on the slope.
Action: Schedule on Consent Agenda
5. Street Dedication for 216th St. SW adjacent to Edmonds Woodway High School
Mr. English explained one of the requirements of the Edmonds-Woodway High School field
improvements was a street dedication to increase the width of 216th Street SW to 60 feet of right-of-way
as required by the City Street Map. There will be no changes to the sidewalk or street.
Action: Schedule on Consent Agenda
6. Frances Anderson Roofing Bid Refusal
Mr. Williams explained the City received a grant two years ago through the State capital budget process
of $391,400. Department of Commerce management expenses and design left approximately $350,000
for roof construction costs. The project was put out to bid in January 2019 and two bids were submitted
for $500,000 and $566,000. The engineer’s estimate was $400,000. Staff research found redoing the
historic parapets was outside the roofers’ expertise. That aspect of the project was removed from the
project and it was put out to bid again. One bid in the amount of $425,000 was received. With only one
bid that was above the engineer’s estimate, he was not comfortable accepting the bid. Staff’s intent is
to provide more flexibility in the specifications and rebid; the original bid specified a roofing system,
Siplaste, which was recommended by the architect who designed the roof and the parapets. He
requested Council reject the bids.
Discussion followed regarding the limited number of companies certified to apply Siplaste, current
roofing material, whether leaks were causing structural damage, and the time required to redo specs
and rebid.
Action: Schedule on Consent Agenda
The meeting was adjourned at 7:30 p.m.