Loading...
Inspection Correction Notice - 390 Sunset.doc CITY OF EDMONDS CORRECTION NOTICE ENGINEERING DIVISION (425) 771-0220 City Website: www.edmondswa.gov DATE: November 17, 2015 PERMIT NUMBER: BLD20150224 OWNER: SITE CONTACT: Neuman ADDRESS: 390 Sunset TYPE OF INSPECTION: Violation WORK DESCRIBED BELOW HAS BEEN INSPECTED AND APPROVED APPROVED PLANS AND PERMIT JOB CARD MUST BE AVAILABLE TO INSPECTOR ON SITE CORRECTIONS LISTED BELOW MUST BE MADE BEFORE WORK CAN BE APPROVED AND/OR THE NEXT PHASE OF WORK IS STARTED. RECALL FOR INSPECTION REINSPECTION FEE MUST BE PAID PRIOR TO NEXT INSPECTION REQUEST. STOP WORK UNTIL AUTHORIZED TO CONTINUE BY CITY INSPECTOR th According to conversation with the lead contractor on site, Thursday November 5, it was th understood that the sidewalk was to be opened by the end of the week of November 9. If sidewalk was to be constructed within the week, a temporary path of gravel was to be placed until required frontage improvements were constructed or temporary asphalt was to be placed. Please address the following issue. 1.At this time the city requires the sidewalk be re-opened by the end of day Thursday November th 19. A path of temporary asphalt 5’ in width shall be placed in line with the existing sidewalk. Any other obstructions, such as sanitary cans, shall be removed from the right of way. th -The city inspector will stop by Friday November 20 to verify the work has been completed and the sidewalk is open. For inspection scheduling call 425-771-0220 x1326. a.If it is intended to construct the frontage improvements within one week time (by 11/18/15), compacted gravel would be an acceptable temporary path where a hard surface (concrete or asphalt) is not currently established. b.If the frontage improvements are not scheduled to be constructed by 11/18/15, temporary asphalt 5’ in width shall be placed in line with the existing sidewalk. Page 2 of 2