pln20080046-Engineering-Final_Plat-memo.pdfCITY OF EDMONDS
ENGINEERING DIVISION
Date: June 26, 2014
To: Michael Clugston, Associate Planner
From: Jeanie McConnell, Engineering Program Manager
Subject: PLN20080046, Shoreshire - Final Plat
24223 76th Ave W — 7 Lot Plat
The Engineering Division has found that the subject 7-lot plat meets the requirements
established for civil subdivision improvements in accordance with Edmonds Community
Development Code (ECDC) 20.75.
The Hearing Examiners Decision, which provided preliminary plat approval, was issued on
October 15, 2008 and included engineering conditions of approval in Exhibit 13. Civil
construction plans were submitted to the Engineering Division on October 25, 2012 consistent
with the conditions of approval and ECDC 20.75.120. The plans were approved for
construction on April 22, 2013. While most of the improvements have been installed and
inspected, the plat construction has yet to be completed in it's entirety. Consistent with
ECDC 20.75.130, a performance bond has been posted as surety that these improvements will
be completed within 12 months following recording of the plat. The performance bond was
submitted by the developer and accepted by the City on June 14, 2013 reflecting the total cost
to construct all required improvements in the amount of $421,862.64.
As a condition of development the subject plat will dedicate a public street to the City of
Edmonds designated as 243rd Pl W. In addition, a 15-foot wide public sanitary sewer utility
easement will be granted to the City of Edmonds. These elements were reviewed by the
Council's Planning, Parks and Public Works committee on April 8th and will be officially
accepted by the City when Council approves the Final Plat resolution.
City of Edmonds