Loading...
SupplemenatGeotPeerReview_tm.pdf Civil Engineering Drawings (4 sheets, including Coversheet, TESC Plan, Drainage Plan, and Details), prepared by Site Development Services, PC, revision dated July 9, 2014. Tobiason, Laurey. 2014. Email message from Laurey Tobiason, President, Principal Planner/Landscape Architect Cert. #305 to Kristin Johns, City of Edmonds, Re: Saunders Permit. July 17. Architects NW. 2014. Letter: City of Edmonds Rev #1 - Response to Landau. From Cory Buckland, Architect NW, Inc. to City of Edmonds. July 17. City of Edmonds. 2014. Affidavit of Earth Subsidence Landslide Hazard Area Permit Posting. April 7. Structural Plans (5 sheets including S1 through S5), prepared by Architects Northwest Inc., revision dated July 10, 2014. Architectural Plan Set (15 sheets, including Sheets A0, A0.1, A1.1, and A2 through A13) prepared by Architects Northwest, Inc., revision dated July 10, 2014. Topographic & Boundary Survey, Saunders Property (2 sheets), prepared by GeoDimensions, revision dated July 14, 2014. Landscape Plan (1 sheet), prepared by Tobiason & Company, Inc. revision dated July 10, 2014. The following briefly reiterates the review comments contained in our April 18, 2014 technical memorandum and states how our review comments were addressed in the most recent resubmittal. Review Comment: A tree cutting/land clearing plan, or a letter or a report stamped by an appropriate licensed design professional, with sufficient information or data to demonstrate why this item is inapplicable. Response: Tree cutting is not proposed as part of this project, and as a result, a tree cutting/land clearing plan is not required. This was confirmed by Leif Bjorback in an email to Landau Associates dated August 6, 2014. Review Comment: An affidavit to verify and document that a notice of permit submittal application has been posted conspicuously at the subject property in accordance with ECDC 20.03.002. The affidavit should be notarized. Response: A notarized affidavit was included in the most recent resubmittal. LA ANDAU SSOCIATES 8/13/14 P:\\074\\177\\FileRoom\\R\\SupplemenatGeotPeerReview_tm.docx 2 Review comment: The geotechnical report should be revised or a supplementary letter submitted that provides anticipated tip elevations/depths for the proposed 4-inch diameter pipe piles based on the recommended pile driving criteria. Response: The most recent resubmittal includes a supplementary letter from Geo Group Northwest, Inc. that provides an anticipated pile depth for the proposed pipe piles based on the recommended pile driving criteria. Review Comment: The anticipated pile tip elevations should be compared to the depths of the borings conducted for this project to determine if the depths of the borings satisfy the minimum depth requirement. Response: The most recent resubmittal includes a supplementary letter from Geo Group Northwest, Inc. that confirms the depths of their borings meet the minimum borehole depth requirement when compared to the anticipated pile length. Review Comment: An addition to the civil plans should include fill/soil stockpile limitation provisions in accordance with ECDC 19.10.030. Response: The civil plans were revised to include fill/soil stockpile limitation provisions in accordance with ECDC 19.10.030. Review Comment: The civil plans should be revised to reflect such provisions, including specific location(s) for stockpiling, height restrictions on stockpiles, and guidelines for protection and maintenance of stockpiled fill/soil. Response: The civil plans were revised to include the above listed information. Review Comment: We also recommend that the civil plans include notes that explain the ECDC st limitations on site access and special inspection requirements for TESC between October 1 and April th 30. Response: Sheet A1.0 of the most recent resubmittal includes a note that limits site work to the dry summer months in accordance with the recommendations contained in the project geotechnical report. Sheet A1.0 also includes a list of activities that will require special inspections. In addition, Sheet 1 of the Civil Plans was revised to include grading and erosion control notes, including notes related to site stth access and stabilization of exposed soil from October 1 through April 30. LA ANDAU SSOCIATES 8/13/14 P:\\074\\177\\FileRoom\\R\\SupplemenatGeotPeerReview_tm.docx 3 Review Comment: These procedures, including compaction criteria, should be incorporated into Sheet A1. Structural fill and its compaction criteria should be specified on this sheet, as well. Response: This information was included on Sheet A1.1 of the most recent resubmittal. Review Comment: Provisions for slab-on-grade floors should be incorporated into the structural plans. Response: This information was included on Sheet A1.1 of the most recent resubmittal. Review Comment: The should include the lowest footing (or bottom of pile cap) elevations of the proposed residence. Response: The most recent resubmittal includes the above listed information. Review Comment: A separate topographical drawing should be submitted showing proposed grade contours at two-foot intervals and the bottom elevations of proposed footings (or pile caps), including all stepped footing (or pile cap) elevations. Response: The most recent resubmittal includes the above listed information. * * * * * * This technical memorandum has been prepared for use by the City of Edmonds in evaluating the adequacy of permit submittal documents related to the proposed Saunders single family residence at th 15911 74 Place West. The focus of this review was the geotechnical aspects of the resubmitted application. The purpose of the review was to assess the adequacy of the application documents for compliance with City requirements contained in ECDC Chapters 19.10 and 23.80 and conformance with conventionally accepted geotechnical engineering practices. This supplemental geotechnical peer review d other design professionals to prepare an appropriate design for the site conditions. We appreciate this opportunity to be of service to the City. Please contact us if you have any questions or if we may be of further service. SZW/rgm LA ANDAU SSOCIATES 8/13/14 P:\\074\\177\\FileRoom\\R\\SupplemenatGeotPeerReview_tm.docx 4