ENG2021-0146 ROW PERMITOF WAY EUC PERMIT
PERMIT NUMBER
City of Edmonds
EdmondsRIGHT
98020 1 1 .
www.cityofedmonds.gov
Description: PSE-INSTALL GAS SERVICE ISSUED: 05/12/2021
Address: 809 8TH AVE S EDMONDS WA 98020-4081
EXPIRES: 11/12/2021
it Type: RIGHT OF WAY EUC Permit Subtype: MINOR Parcel Number: 00455800000200
I 11-1411 a
W
NAME TYPE NAME ADDRESS PHONE
APPLICANT PSE/INFRASOURCE 1660 PARK LANE, BURLINGTON WA 98233 (425)457-6353
CONTRACTOR PSE/INFRASOURCE 1660 PARK LANE, BURLINGTON WA 98233 (425)457-6353
OWNER SADLER TIMOTHY & HEIDI 809 LAUREL WAY, EDMONDS WA 98020
FEE INFORMATION
DESCRIPTION AMOUNT PAID
CITY TECHNOLOGY FEE CHARGED PER PERMIT
$40.00 $0.00
ENGINEERING INSPECTION FEE
$220.00 $0.00
RIGHT OF WAY MINOR - EUC PERMIT FEE
$110.00 $0.00
•
REQUIREMENT TYPE
NOTES
TRAFFIC CONTROL Traffic control and public safety shall be in accordance with City regulations as required by the City
Engineer. Every flagger must be trained as required by WAC 296-155-305 and must have certification
verifying completion of the required training in their posession.
RESTORATION Restoration is to be in accordance with City codes. All street -cut trench work shall be patched with
asphalt or City approved material prior to the end of the workday - No Exceptions
WARRANTY The contractor is responsible for workmanship and materials for a period of one year following the final
inspection and acceptance of the work.
INSPECTION SCHEDULING: WWW.MYBUILDING PERMIT.COM
24 HR NOTICE REQUIRED
INDEMNITY
The Applicant has signed an application which states he/she holds the City of Edmonds harmless from injuries, damages or claims of
any kind or description whatsoever, foreseen or unforeseen, that may be made against the City of Edmonds or any of its departments
or employees, including but not limited to the defense of any legal proceedings including defense costs and attorney fees by reason of
granting this permit.
THIS DOCUMENT IS NOT VALID UNTIL FEES ARE PAID AND THE CITY ENGINEER OR HIS/HER DEPUTY HAS SIGNED BELOW
05/12/2021
VAI!>/F9:1H ]1
DATE
Printed: Wednesday, May 12, 2021 11:15:59 AM 1 of 2
-KRWOF WAY EUC PERMIT
City of • • •
•:• • ENG2021-0146
www.cityofedmonds. ov/425.771.0220
CONDITIONS
CONDITION TYPE
Easement and/or permission from adjacent property owner is required prior to entry or work within
ADJACENT PROPERTY
an adjacent property.
It is the owner's responsibility to repair/replace all damage of utilities or frontage improvements in
DAMAGE TO FRONTAGE
City right of Ways or Easements to City Standards caused by or occurring during the permitted
IMPROVEMENTS
project.
Alert affected residents and/or businesses prior to work start.
Verify clear bore crossings.
ENGINEERING OTHER
Restore landscape to like or better conditions.
Call for required inspections as noted.
ESC REQ
Maintain erosion and sedimentation control per City and SWMMW standard requirements.
Applicant, on behalf of his or her spouse, heirs, assigns, and successors in interests, agrees to
indemnify defend and hold harmless the City of Edmonds, Washington, its officials, employees, and
agents from any and all claims for damages of whatever nature, arising directly or indirectly from the
HOLD HARMLESS
issuance for this permit. Issuance of this permit shall not be deemed to modify, waive or reduce any
requirements of any City ordinance nor limit in any way the City's ability to enforce any ordinance
provision.
Sound/Noise originating from temporary construction sites as a result of construction activity are
exempt from the noise limits of ECC Chapter 5.30 only during the hours of 7:OOam to 6:OOpm on
SOUND OR NOISE
weekdays and 10:OOam and 6:OOpm on Saturdays, excluding Sundays and Federal Holidays. At all
other times the noise originating from construction sites/activities must comply with the noise limits
of Chapter 5.30, unless a variance has been granted pursuant to ECC 5.30.120.
All utilities shall be located prior to any excavation. New locates shall be called for if at time of
UTILITY LOCATES
excavation, original locates are no longer identifiable.
INSPECTION TYPE
DATE
RESULT
NOTES
COMPLETE
A-1 JOB START
E-7 RESTOR LIMITS
X-2 ENGINEERING FINAL"
E-7 CURB GUTTER
Printed: Wednesday, May 12, 2021 11:15:59 AM 2 of 2
of EpM04O�
RIGHT OF WAY CONSTRUCTION
PERMIT APPLICATION
Complete and submit this Application in accordance with the Submittal
/'Vc. i aa° Requirements outlined in Right -of -Way permit Handout E6�.
If any field is not applicable to your project, write "N/A' instead of leaving blank.
All fields required. Incomplete Applications will be denied.
SECTION A
General •
Project Name 109137115
Site Address or if no site address use Property Address at NW corner of project area: 8o9 Laurel Way
Associated Permits: BLD PLN ENG x
Owner and Entity Holding Franchise (if applicable)
Name of Company pSE/Infrasource Franchise Ordinance No:
Point of Contact Susan Sidick
Title SR Permit Specialist
Address 166o Park Lane
City Burlington
State WA
Zip 98233
Phone 2 - -6
Email
susan.sidick0pse.corn
Contractor and Authorized Agent of Owner
Name of Company pSE/Infrasource
(see note below)
Contractor Contacts During Construction
Primary Name
Agent Name Susan Sidick PSE/Infrasource
Title Sr Permit Specialist
Title Sr Permit Specialist
Mobile 425-457-6353
Address 166o Park Lane
Email susan.sidickOpse.com
City Burlington
State WA
Zip 98233
Secondary Name
Phone 425-457-6353
Title
Email susan.sidick@pse.com
Mobile
City of Edmonds Business License No:
Email
State License No: INFRASL871C2
EX Contractor verifies it is currently bonded
Contractor verifies it currently has general liability insurance
NOTE: ECDC 18.6o. o2o requires that the Application be signed by a licensed and bonded contractor unless otherwise approved by the city
engineer.
❑ Multifamily residential ❑ Commercial ❑ City project
❑ Single family residential subdivision ixSingle family -other ❑ Industrial
❑ Demo and rebuild or from vacant land?
❑ Other, please specify:
❑ Utility Franchise Work associated with development (check one of the above boxes as welt
❑ Traffic Control Only (no associated development)
iNUtility Franchise Work (no associated development)
City of Edmonds ROW construction permit Application --Page 1 of 3 Updated 3/25/2021
Include an overall narrative description of the proposed work. Be specific and detailed:
Describe infrastructure to be impacted, such as, poles, wires, conduit, utility mains, etc.
Include whether this is construction, maintenance, or repair.
Include description of proposed construction methods, (e.g., bores, trenches, overhead wires proposed, depth for
underground utilities, etc.)
From 2" STW run complete 1 -1/8 PE altered service work area is approx WN c/l of Laurel Way & 55' E c/l of 8th
AVE S underjob #109137115 1 3x5 concrete grass
RIGHT-OF-WAY
CLOSURE
AREA
TOTAL
DURATION
(Number of Months)
Sidewalk 72 hours +
LF
I x
LF
SF
Alley 72 hours +
LF
Ix
I LF
SF
Parking 72 hours +
LF
Ix
I LF
1 SF
SECTION B - If you are not a utility company performing work in the City ROW, skip to SECTION C.
1. The work in the right of way is on or for the following type of facilities:
❑ telecommunications ❑ cable ❑ power )o gas
❑ water ❑ sewer ❑ storm
Details of Work to be Completed
1. Does the utility owner have existing overhead infrastructure in the area of work?
Yes
No
x
2. Will any equipment be added underground or above ground (e.. pedestals, vaults, etc.)?
x
If yes, describe:
3.
Does the proposed work connect a lot or commercial development with utilities that serve more
than one lot or commercial development?
x
4.
Does the work involve rebuilding or relocating an existing aboveground utility system which
connects a lot or commercial development to an existing underground common utility stem?
x
5.
Does the work involve proposed additions to an aboveground utility stem? If es:
Are the additions for the purpose of serving new commercial development?
Are the additions for the purpose of serving a single-family residential subdivision?
Details
of Work to be Completed
Yes
No
6.
Does your project involve rebuilding or replacing utility equipment which currently serves more
than one lot or commercial development?
If yes, answer the following questions related to project area, i.e. the actual area in which the
project is proposed:
x
6a.
Does your project involve wires/cables/lines? If yes:
x
How many are existing? I I How many are to be added?
City of Edmonds ROW construction permit Application --Page 2 of 3 Updated 3/25/2021
6b.
Does your project involve poles? If yes:
no
How many poles are existing in the project area?
What is the height of the existing poles?
How many poles are to be removed?
Are additional poles to be laced?
How many? I I What is the height of the additionalpoles?
6c.
Are any poles to be modified/rebuilt/replaced? If yes:
How many? I I What is the height of the poles after?
Describe the modification rebuild:
SECTION C
Traffic Control and Public Safety. Traffic control and public safety shall be in accordance with City regulations as
required by the City Engineer. Every flagger must be trained as required by WAC 296-155-305 and must have
certification verifying completion of the required training in their possession.
Restoration. Restoration shall be in accordance with City codes and Standards. All street cut trench work shall be
patched with asphalt or City approved material prior to the end of the workday -NO EXCEPTIONS.
Insurance. The City may require the owner or contractor to provide proof of insurance acceptable to the City prior to
any permit approval.
Indemnification. The Applicant agrees to defend, indemnify, and hold harmless the City of Edmonds, its officials,
officers, employees, and agents against any injuries, damages, or claims of any kind or description whatsoever,
foreseen or unforeseen, including defense costs and attorney fees, resulting directly or indirectly from any act or
omission of the Applicant, its subcontractors, anyone directly or indirectly employed by them, and anyone for whose
acts or omissions they may be liable, arising out of, related to, or by reason of the granting of this permit; and
specifically including but not limited to all loss by the failure of the Applicant to fully or adequately perform, in any
respect, all authorizations or obligations under the permit. These indemnification requirements shall survive the
expiration, revocation, or termination of any resulting permit approval.
Acceptance of terms, conditions, and requirements. Applicant accepts the terms, conditions, and
requirements set forth in this Application and agrees they apply to any resulting permit and shall comply with them to
the satisfaction of the City Engineer. Applicant further agrees to comply with the conditions listed on the Submittal
Requirements; with all applicable city ordinances, including but not limited to ECDC Title 18; and with all applicable
requirements of state and federal law.
Statement of Applicant. I declare under penalty of perjury under the laws of the State of Washington that: I am a
licensed and bonded contractor; the information provided herein is correct and complete; and I am authorized by
owner to act on its behalf and have authority to bind the owner to this application.
Fees. The Applicant is responsible for all permit fees.
APPLICANT SIGNATURE: Susan Sidick DATE: 04/26/202i
APPLICANT PRINTED NAME: SusanSidick
APPLICANT TITLE: SR permit Specialist
NO WORK SHALL BEGIN PRIOR TO PERMIT ISSUANCE
City of Edmonds ROW construction permit Application --Page 3 of 3 Updated 3/25/2021
Puget Sound Energy
Traffic Control Supervisor:
Gregory Harwood
Card No. 012238
Card Exp. 09/30/2023
gregory.harwood@pse.com
(425)424-6425
=p� t
Y a�8
d. o
PLACE SIGNS
BOTH SIDES OF
WORK AREA
A
LAUREL ST
Applicant shall repair/replace all
damage to utilities or frontage
improvements in City right-of-way
per city standards that is caused or
occurs during the permitted project.
TEMPORARY TRAFFIC CONTROL PLAN
V
b V
OWNER/CONTRACTOR IS RESPONSIBLE FOR
EROSION CONTROL AND DRAINAGE
LEGEND
®
28" TRAFFIC CONE
®
WORK PIT
TRAFFIC FLOW
WORK VEHICLE/
FLASHING LIGHTS
SIGN LOCATION
RIGHT OF WAY
ROW
SIGN SPACING
MPH
"X"
60/65
1000,
45/55
500,
35/40
350'
30
200'
25
1 100'
H3Hb
o \Adom
IV08.
co
U
Q
CHANNELIZATION
DEVICE SPACING
MPH
TAPER
TANGENT
55/70
40
80
35/45
30
60
25/30
20
40
17 17
PUGET
� SOUND
ENERGY
JOB# 109137115
809 Laurel Way, Edmonds, WA
April - 23 - 2021
ina.ustemchuk@pse.com
(425)398-6063
SHEET 1 of 1
RESIDENT(S) WILL BE INFORMED
OF POSSIBLE TEMPORARY
DRIVEWAY CLOSURE
ENGINEERING DIVISION
APPROVED AS NOTED
S-I,ZM
809 o
o�
LAUREL WAY
b
05/06/2021
MAINTAIN TWO 11' TRAVEL LANES,
17 OTHERWISE USE FLAGGERS AND
4 SINGLE LANE CLOSURE SIGNS.
0
0
ROAD
WORK
AHEAD CN
RECEIVED
APR 26 2021
CITY OF EDMONDS
DEVELOPMENT
SERVICES DEPARTMENT
Notes:
1. All signs and spacing to conform to the MUTCD
and City of Edmonds standards.
2. All sidewalks, driveways, exits and egresses
shall be completely clear unless otherwise indicated.
3. Channelizing devices are 28" traffic cones.
Use traffic drums (barrels) with steady burning
Type C lights on all State Routes and Hwys.
4. Sign size can be a minimum of 36" x 36" and shall
not obstruct pedestrian access.
5. Crew is required to leave a minimum of 11' for
traveling lane width.
6. Alert affected residents and businesses.
7. Work to take place between 9 a.m. and 4 p.m
unless otherwise specified. All work for arterials
and major roadways will be from 9 a.m. to 3 p.m
8. Work area will be 16' NCL of Laurel Way & 55' ECL of
8th Ave S.
9. If used, place NO -PARK signs 72 hours in
advance of the day that the work is to be done.
RECEIVED
Job #:
Date:
Jurisdiction:
ROW Permit:
Est. Start Date:
Est. Duration:
Puget Sound Energy Gas Pre -Inspect Form
109137115
4/19/21
Edmonds
Yes
6/28/21
1-112 Days (12 hours)
APR 26 2021
Address: 809 LAUREL WAY
City / Zip: Edmonds, 98020 clnF OFnDDMONDS
MENT
Customer: TIMOTHY SADLER 206-992-6198 SERVICES DEPARTMENT
PM / Inspector: kevin Williams 425-691-7573
Job Description / Scope of Work
From 2" STW run complete 1 -1/8 PE altered service to SFH 809 (9' scat stub with 71' scat ext.)
New Construction:
No
Set 425 meter
OL @ Inches,
also cut and cap service branching from home 801.
Construction Method
All Scat / Trenchless
PLAT Map:
164.066
t
fN
I
HEML OCAY
'
I
801
II
760
I
II
' 1 5/8" PE
MPE
1
I I 1981
E
1
425 4 C&C
821
PS-0353
I Q
I 1 Bush Tree 5/8" PE
109040732
1
85'S,23'
_ 1 �
I I MO1981
BUS 0
1
BUS" 809
85S,14'W
Deep
I '
5/8" PE
10904073 200 3�
i i Bush
1993 1 1 /4" E IP 3
`0 `o
�Bus Bush
93 49
T T
w
II __---__---- ;O
6' N
__
1 93268411-114 PE IP 16
RtE L V„ �
II Y
---
Water
III
-------------
—----------------------storm
I
II
ROW 50'
_
Work
Location
Size of Cut
Surface Type
16'
N
of CL
LAUREL WAY
&
55'
E
of CL
8th AVE S
3x5
Concrete/Grass
of CL
&
of CL
of CL
&
of CL
Service Information
Street Information
Job Type
Diameter:
1-1/8" PE
Flaggers #:
No
Arterial:
No
Altered Residential Svc
EFV:
1-1/8" - 2600 - 9999144
Police #:
No
TCP:
Yes
Tie -In Fitting
Meter:
A425
Speed Limit:
25
No Parks #:
Meter Loc:
0
Trolley Lines:
Mtr Hoods #:
Del Press:
6" W.C.
Traffic Signal:
Bus Stop:
Bollards:
2.5" #
4" #
ADA Ramps #:
Route #'s: